Last spring I looked at a job-
It involved excavating a backyard extensively and creating a large retaining wall that had to be certified by an engineer-
Building a room addition into that area
Building a masonry storm shelter in the house
Converting the attached garage into a living suite
Removing the middle loadbearing wall in the house and installing a large LVL to spend the distance and carry the roof load
Fully re-wiring and
replumbing the house
Completely altering and renovating every square inch of the interior with four full tile bathrooms
New floors new trim new drywall, paint, new cabinets... the whole shebang and exterior accents and painting the house along with probably 40 yards of concrete
The architect told the lady she should be able to do this for about $200,000.
I really didn’t even want to talk further with her so out of touch and told her that she was looking in the 350 to 400 range depending on her tastes- I was very cordial and curious at how determined she was to get it done so dangerously cheap.
I reached out to her about a week later and asked her what she was thinking and she said she had contractor and she was just fine.
Well of all things later I ran into a contractor buddy of mine a little while later and he was telling me about this certain job and it turns out that he took the job- for 262,000.00
They end up getting the job about 90% done and 4 months behind his promised completion date and are having tremendous friction between him and her and can’t get paid - I told him to stop the job and get a completion plan, collect the needed money and get it finished. Then settle up.
I was amazed to learn he had no payment schedule in his contract.
The entire contract was literally four sentences. Less than one page.
He would not listen to me and things basically just kept falling apart. He kept going. Big mistake. Next a vendor mails her a lien threat and she freaks and gets a lawyer.
Now they are having a Mexican standoff.
Recently she reaches out to me and invited me to come look at the house.
At this stage she owes him 60,000 and she’s nervous about giving him more money and asked me if I think there is $200,000 of work done there.
I told her “no, I think there’s about $350,000 worth of work done and that the reason he can’t finish is he’s out of money.”
She told me she would’ve hired me but he was all she could afford.
I told her well she couldn’t afford him either he just did not know that.
When I walked through the house basically I was just going “oh God, Oh God, oh God” mentally. I had a feeling he was in trouble on the project but when I saw that I realized he probably lost $160,000. Just the masonry cost was $50,000 and at that point he had suck his boat as that was nearly 20% of the gross contract.
He has drained his company,
The good side is the work is in a logical state of completion and beautifully executed- He could’ve done a few things better but I can say the same for myself at times.
With the money she has they can go a long way to getting it finished but I think they’re going to run into trouble on the cost of concrete because they have a pretty good bit of yardage.
The bad news is he got no engineer to sign off on the retaining wall, This is a huge problem getting a certificate of occupancy. And he owes a lot of people money so subcontractors are not too quick to come.
And of course she’s looking to me for advice so here is what I told her- Keep in mind I was aware of some things he has requested she do to move things along.
I told her to go to the plumbing supply place and pay for every single thing you need and get the sinks and faucets delivered to the countertop fabrication company-
Locate all the cabinets that you intend to purchase for the bathrooms and get them purchased and delivered.
Locate your interior door hardware.
Get your structural engineer buddy to help you guys with the retaining wall certificate it may require some excavation to verify it was done correctly.
Get your light fixtures to the house.
Get the countertop template didn’t get an installation date and schedule the plumber with him.
Figure out how much concrete you need and the cost - If you don’t think you’re going to be able to do it I’ll figure out what is absolutely essential.
Get a count on all your cabinet doors and order your cabinet hardware
Get your shower glass quoted and make a decision on what to order
Get a lien waiver signed for any money you give him and anywhere you can pay people with joint checks- to him and them- They can give him his profit out of the transaction ( Which won’t happen because he owes everybody in town money right now- me included)
Once you guys have a handle on this you need to lay out your money on paper look at what you spent that was going to go to him and see what you have left determine what is fair and make sure when the money moves it moves people.
Lord have mercy.
There are so many things wrong with this situation-
Let me take a minute to explain how things like this happen-
- Contractors get busy and they don’t slow down and look at the constructibility challenges of a project during the bid phase
- They get overconfident in their success and don’t even consider that they could make a serious mistake
- They start running into financial issues and will take work at a ridiculously low price in order to make sure they get the job to get some money coming in trying to keep everything going
- They dramatically overestimate their capability to execute work within budget- As if they are somehow immune to the current market price of products and services
-They write sloppy contracts
- they spend money that is not theirs to spend
- They don’t know their own costs
Some or all of this happens, then the money slows down, the work slows down, that slows down the money even more ......
He and I are going to sit down in a day or two and I’m going to share some things that have helped me through some tough situations and hopefully he can muscle through this. He has been through some hard things and overcome them in the past and worked hard to get where he is.
It involved excavating a backyard extensively and creating a large retaining wall that had to be certified by an engineer-
Building a room addition into that area
Building a masonry storm shelter in the house
Converting the attached garage into a living suite
Removing the middle loadbearing wall in the house and installing a large LVL to spend the distance and carry the roof load
Fully re-wiring and
replumbing the house
Completely altering and renovating every square inch of the interior with four full tile bathrooms
New floors new trim new drywall, paint, new cabinets... the whole shebang and exterior accents and painting the house along with probably 40 yards of concrete
The architect told the lady she should be able to do this for about $200,000.
I really didn’t even want to talk further with her so out of touch and told her that she was looking in the 350 to 400 range depending on her tastes- I was very cordial and curious at how determined she was to get it done so dangerously cheap.
I reached out to her about a week later and asked her what she was thinking and she said she had contractor and she was just fine.
Well of all things later I ran into a contractor buddy of mine a little while later and he was telling me about this certain job and it turns out that he took the job- for 262,000.00
They end up getting the job about 90% done and 4 months behind his promised completion date and are having tremendous friction between him and her and can’t get paid - I told him to stop the job and get a completion plan, collect the needed money and get it finished. Then settle up.
I was amazed to learn he had no payment schedule in his contract.
The entire contract was literally four sentences. Less than one page.
He would not listen to me and things basically just kept falling apart. He kept going. Big mistake. Next a vendor mails her a lien threat and she freaks and gets a lawyer.
Now they are having a Mexican standoff.
Recently she reaches out to me and invited me to come look at the house.
At this stage she owes him 60,000 and she’s nervous about giving him more money and asked me if I think there is $200,000 of work done there.
I told her “no, I think there’s about $350,000 worth of work done and that the reason he can’t finish is he’s out of money.”
She told me she would’ve hired me but he was all she could afford.
I told her well she couldn’t afford him either he just did not know that.
When I walked through the house basically I was just going “oh God, Oh God, oh God” mentally. I had a feeling he was in trouble on the project but when I saw that I realized he probably lost $160,000. Just the masonry cost was $50,000 and at that point he had suck his boat as that was nearly 20% of the gross contract.
He has drained his company,
The good side is the work is in a logical state of completion and beautifully executed- He could’ve done a few things better but I can say the same for myself at times.
With the money she has they can go a long way to getting it finished but I think they’re going to run into trouble on the cost of concrete because they have a pretty good bit of yardage.
The bad news is he got no engineer to sign off on the retaining wall, This is a huge problem getting a certificate of occupancy. And he owes a lot of people money so subcontractors are not too quick to come.
And of course she’s looking to me for advice so here is what I told her- Keep in mind I was aware of some things he has requested she do to move things along.
I told her to go to the plumbing supply place and pay for every single thing you need and get the sinks and faucets delivered to the countertop fabrication company-
Locate all the cabinets that you intend to purchase for the bathrooms and get them purchased and delivered.
Locate your interior door hardware.
Get your structural engineer buddy to help you guys with the retaining wall certificate it may require some excavation to verify it was done correctly.
Get your light fixtures to the house.
Get the countertop template didn’t get an installation date and schedule the plumber with him.
Figure out how much concrete you need and the cost - If you don’t think you’re going to be able to do it I’ll figure out what is absolutely essential.
Get a count on all your cabinet doors and order your cabinet hardware
Get your shower glass quoted and make a decision on what to order
Get a lien waiver signed for any money you give him and anywhere you can pay people with joint checks- to him and them- They can give him his profit out of the transaction ( Which won’t happen because he owes everybody in town money right now- me included)
Once you guys have a handle on this you need to lay out your money on paper look at what you spent that was going to go to him and see what you have left determine what is fair and make sure when the money moves it moves people.
Lord have mercy.
There are so many things wrong with this situation-
Let me take a minute to explain how things like this happen-
- Contractors get busy and they don’t slow down and look at the constructibility challenges of a project during the bid phase
- They get overconfident in their success and don’t even consider that they could make a serious mistake
- They start running into financial issues and will take work at a ridiculously low price in order to make sure they get the job to get some money coming in trying to keep everything going
- They dramatically overestimate their capability to execute work within budget- As if they are somehow immune to the current market price of products and services
-They write sloppy contracts
- they spend money that is not theirs to spend
- They don’t know their own costs
Some or all of this happens, then the money slows down, the work slows down, that slows down the money even more ......
He and I are going to sit down in a day or two and I’m going to share some things that have helped me through some tough situations and hopefully he can muscle through this. He has been through some hard things and overcome them in the past and worked hard to get where he is.
Last edited:
